NYSDEC Superfund Sites
Honeywell has completed the initial site investigation. Completion of a supplemental investigation is anticipated to be completed in March 2023 at Site 108, which is adjacent to the Niagara River. The company worked proactively with EPA since late 2018 to address priority environmental issues associated with Site 108.
Sites 109 and 110 were previously investigated and a remedial decision was issued under the state Superfund Program. However, these two sites are being further investigated, and a Focused Feasibility Study will be prepared to determine if the change in site use warrants additional remedial action.
Site 108 Work (Adjacent to Niagara River)
- Initial and majority of supplemental field work completed.
- Draft Remedial Investigation Report submitted to NYSDEC in January 2022; agency provided comments in April 2022; report will be revised following completion of the supplemental investigation.
- Final Supplemental Investigation Work Plan submitted to NYSDEC in August 2022 and approved by NYSDEC in September 2022.
Completed work:
- Collection of surface soil samples
- Excavation of test pits and collection of subsurface soil samples
- Installation and sampling of groundwater monitoring wells, including on the adjacent National Grid and Erie Canal properties
- Collection of sediment samples from onsite and off-site including a portion of the Niagara River
- Removal of three large above ground coal tar storage tanks as approved and overseen by US EPA, including:
- Removal and offsite disposal of water and tar from within the tanks
- Demolition, decontamination, and offsite disposal of the tanks
- Excavation and offsite disposal of contaminated soil adjacent to the tanks that had resulted from prior releases from the tanks
- Backfilling and site restoration
- Removal and off-site disposal of contaminated soil piles that remained on site from prior cleanup activities
- Asbestos removal and offsite disposal
- Air monitoring during storage tank demolition and intrusive activities; results are posted here
Site 109 and Site 110
Site 109 is located just east of River Road on the western side of the main parcel. In 1977, an unknown quantity of brick, rubble, and related demolition waste was disposed in this area. Site 110 is in the northeast corner of the property east of River Road at the rear of the former plant. Materials such as coal tar sludge, fly ash and cinders were reportedly disposed of in this area. The disposal activities occurred prior to 1978.
- Initial and supplemental field work completed
- Draft Remedial Investigation Report sent to NYSDEC in April 2022; agency provided comments in August 2022; report will be revised following completion of the supplemental investigation
- Final Supplemental Investigation Work Plan submitted to NYSDEC in August 2022 and approved by NYSDEC in October 2022
Completed work:
- Collection of surface soil samples
- Excavation of test pits and collection of subsurface soil samples
- Installation and sampling of groundwater wells
- Air monitoring during intrusive activities; results are posted here
Off-Site Ponds
- Site Characterization Report submitted to NYSDEC October 21, 2021